Water flowing through Lewis & Clark pipeline
Published: July 30, 2012
By:
Tags: Lewis & Clark Regional Water System, Red Arndt, Vermillion
Tea, SD β Water started flowing Monday through the Lewis & Clark Regional Water System after more than two decades of planning and construction.
A treatment plant near Vermillion began producing water for distribution to 11 of the 20 member cities and rural water systems, including Sioux Falls.
The regional water system was incorporated in January 1990 with the goal of supplying 300,000 people in South Dakota, Minnesota and Iowa with water from the Missouri River.
“With our members unfortunately experiencing critical water needs in the face of a crushing drought, we are extremely pleased that Lewis & Clark is able to begin producing water just in the nick of time,” said Board Chairman Red Arndt, of Luverne. “This project has been an enormous undertaking. Words cannot express the range of emotions of finally reaching this point. … July 30 is truly a historic day for Lewis & Clark.”
The $462 million project is not expected to be finished for several years, and federal money for upcoming construction is uncertain because of budget cuts.
“We continue to work tirelessly,” Arndt said, βto ensure the remaining nine members are connected as soon as possible.β
Copyright 2013 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed.
![[Print]](http://dailyreporter.com/wp-content/plugins/tdc-sociable-toolbar/print.png)
![[Email]](http://dailyreporter.com/wp-content/plugins/tdc-sociable-toolbar/email_2.png)