Cullen named CMAR on UW-Madison performance center project (access required)

Published: October 20, 2011
Tags: , , , , , ,

Janesville-based general contractor J.P. Cullen & Sons Inc. was awarded the $76.8 million contract for the Student Athlete Performance Center at the University of Wisconsin-Madison campus, according to a company news release.

State OKs construction manager for UW theater job (access required)

Published: September 28, 2011
Tags: , , , , , , , , , , , , , , , ,

The University of Wisconsin System can use construction-manager-at-risk for its Memorial Union theater project, but the bid opening must be transparent.

Madison project prompts delivery debate (access required)

Published: June 23, 2011
Tags: , , , , , , , , , , , , , , , ,

By James Briggs The construction-manager-at-risk project delivery method is facing renewed scrutiny after state approval of a waiver for the University of Wisconsin-Madison. The state Building Commission granted the waiver Wednesday for a $76.8 million addition to Camp Randall Stadium and the McClain Center called the Badger Performance Center. State and UW-Madison officials argued CMAR [...]

Budget hawk circles Camp Randall project (access required)

Published: June 22, 2011
Tags: , , , , , , , , , , , , ,

By James Briggs A state lawmaker warned the University of Wisconsin-Madison on Wednesday not to exceed the $76.8 million budget for the Badger Performance Center or it will lose his support. State Rep. Dean Kaufert, R-Neenah, said he was worried the university was maxing out its capacity to build projects for the athletics department. Kaufert’s [...]

Wisconsin athletics pushing new $76 million building

Published: August 18, 2010
Tags: , , , ,

By 
COLIN FLY AP Sports Writer MADISON, Wis. (AP) — Wisconsin athletic officials are asking for a $76.8 million athletic performance center in the next two-year state budget, just five years after a $109.5-million expansion of Camp Randall Stadium. The University of Wisconsin System Board of Regents will review the request Thursday. The proposal includes [...]