  • Wall-tech Inc., Madison, reached an informal settlement with OSHA on April 2 to reduce 10 lead citations, totaling $19,250, to $2,750. The company was issued the citations March 18 during a specialty-trade job at 2650 N. Summit Ave., Oconomowoc.
  • Becker Electrical Group Inc., Kenosha, reached an informal settlement with OSHA on April 2 to reduce a $1,925 carbon-monoxide citation to $0. The company was issued the citation March 11 during an electrical job at 10901 38th St., Kenosha.
  • Republic Refrigeration Inc., Monroe, N.C., reached an informal settlement with OSHA on April 3 to reduce a $3,500 temporary-heating-devices citation to $0. The company was issued the citation March 11 during a plumbing, heating and air-conditioning job at 10901 38th St., Kenosha.
  • First Superior Exteriors Inc., Greenfield, reached an informal settlement with OSHA on April 5 to reduce a $750 fall-protection citation to $525. The company was issued the citation April 3 during a roofing job at 16415 Wisconsin Ave., Brookfield.
  • Magaw Electric Construction Inc., Sturtevant, reached an informal settlement with OSHA on April 7 to reduce two electrical-wiring-methods citations, totaling $3,000, to $1,600 and three electrical-installation-safety-requirements citations, totaling $4,500, to $2,400. The company was issued the citations March 30 during an electrical job at 3737 Outer Loop Road, Kenosha.
  • Middleton Construction Inc., Arlington, reached an informal settlement with OSHA on April 8 to reduce a $2,450 temporary-heating-devices citation to $0. The company was issued the citation March 11 during a concrete job at 10901 38th St., Kenosha.
  • JDK Builder LLC, West Bend, reached an informal settlement with OSHA on April 15 to reduce a $1,050 fire-protection citation to $0, a $1,050 electrical-wiring-methods citation to $0, a $1,500 fall-protection citation to $1,000 and a $1,050 stairways citation to $0. The company and OSHA also agreed to dismiss a $1,500 fall-protection citation and a $1,050 stairways citation. The company was issued the citations April 3 during a framing job at 16415 Wisconsin Ave., Brookfield.
  • Brick Stone LLC, Watertown, reached an informal settlement with OSHA on April 22 to reduce a $525 fire-protection citation to $0, a $525 electrical-wiring-methods citation to $300, a $525 scaffolding citation to $300 and a $525 stairways citation to $300. The company was issued the citations April 3 during a masonry job at 16415 Wisconsin Ave., Brookfield.
  • Current Electric Co., Brookfield, reached an informal settlement with OSHA on April 23 to pay a $225 electrical-wiring-methods citation. The company was issued the citation April 16 during an electrical job at 1313 N. Franklin Place, Milwaukee.
  • Speedway Sand & Gravel Inc., Middleton, reached an informal settlement with OSHA on April 29 to reduce a $2,500 requirements-for-excavation-protective-systems citation to $1,750. The company was issued the citation April 15 during a water- and sewer-line job in Madison.
  • Underground Pipeline Construction Inc., New Berlin, reached a formal settlement with OSHA on May 2 to reduce a $900 ladders citation to $450 and two requirements-for-excavation-protective-systems citations, totaling $7,200, to $2,100. The company and OSHA also agreed to dismiss a $1,500 requirements-for-excavation-protective-systems citation. The company was issued the citations Dec. 15 during a water- and sewer-line job in Milwaukee.
  • The Selmer Co., Green Bay, reached a formal settlement with OSHA on June 8 to reduce a $1,500 scaffolding citation to $1,100. The company was issued the citation Jan. 22 during an industrial building and warehouse job in Wittenberg.