• Bonney’s Roofing and Home Improvement LLC, Franklin, must pay a $1,200 fall-protection citation because the period to contest the violation with a Wisconsin OSHA office has ended. The company was issued the citation July 20 during a roofing job at 1334 S. 76th St., West Allis.

• L.J. Contractors LLC, Franklin, must pay a $5,600 fall-protection citation because the period to contest the violation with a Wisconsin OSHA office has ended. The company was issued the citation July 20 during a roofing job in West Allis.

• Ever Clear Construction LLC, Milwaukee, must pay a $2,000 fall-protection citation because the period to contest the violation with a Wisconsin OSHA office has ended. The company was issued the citation May 18 during a roofing job at 18010 W. Ashlea Drive, Brookfield.

• Dan’s Delivery Service LLC, Marshfield, must pay a $2,800 safety-training-and-education citation and a $2,800 equipment citation because the period to contest the violations with a Wisconsin OSHA office has ended. The company was issued the citations July 23 during a specialty trade job at 11298 County Highway H, Marshfield.

• Holton Brothers Inc., Grafton, reached an informal settlement with OSHA on Aug. 16 to dismiss a $4,500 scaffolding citation, pay a $4,500 scaffolding citation and reduce a $3,060 head-protection citation to $0. The company was issued the citations July 25 during a masonry job at 5053 N. Lake Drive, Milwaukee.

VISIT OUR NEW OSHA WEBSITE

• Squared Away Builders Inc., West Bend, reached a formal settlement with OSHA on Aug. 20 to increase a $2,040 scaffolding citation to $2,500 and reduce a $2,550 fall-protection citation to $0. The company was issued the citations March 22 during a framing job at 19760 Bradon Trail, Brookfield.

• Mather Specialty Inc., Burlington, reached an informal settlement with OSHA on Aug. 23 to reduce a $1,530 fall-protection citation to $800. The company was issued the citation Aug. 3 during a roofing job at 6270 S. 108th St., Franklin.

• Carroll Contracting Inc., Broadview, Ill., reached an informal settlement with OSHA on Sept. 4 to reduce a $2,000 fall-protection citation to $1,400. The company was issued the citation Aug. 15 during a masonry job at 115 S. Moorland Road, Brookfield.

• A1 Home Improvements, Markesan, reached an informal settlement with OSHA on Sept. 4 to reduce a $2,800 fall-protection citation to $1,500. The company was issued the citation Aug. 10 during a roofing job at 115 Harvard St., Markesan.

• GP Construction Group Inc., Spring Grove, Ill., reached an informal settlement with OSHA on Sept. 5 to reduce a $2,000 fall-protection citation to $1,200. The company was issued the citation Aug. 16 during a masonry job at 115 S. Moorland Road, Brookfield.

• J&B Construction Co. Inc., Germantown, reached an informal settlement with OSHA on Sept. 6 to reduce a $5,600 fall-protection citation to $3,000, a $1,600 fall-protection-training citation to $0 and a $1,200 head-protection citation to $0. The company was issued the citations Aug. 16 during a roofing job at 314 E. Beechwood Court, Mequon.

• Cedar Creek Carpentry Inc., West Bend, reached an informal settlement with OSHA on Sept. 7 to reduce a $1,360 fall-protection citation to $952. The company was issued the citation Aug. 28 during a framing job at 5265 Juniper Lane, West Bend.

• Rossey Construction Inc., Oconomowoc, reached an informal settlement with OSHA on Sept. 7 to reduce a $1,600 fall-protection citation to $1,120. The company was issued the citation Aug. 16 during a framing job at 1265 Corporate Center Drive, Oconomowoc.

• Buhr Construction Inc., Brussels, reached an informal settlement with OSHA on Sept. 10 to reduce a $1,700 fall-protection citation to $1,190. The company was issued the citation Aug. 16 during a roofing job at 1209 Brookwood Drive, Green Bay.

• Seamless Gutters Unlimited Inc., New Glarus, reached an informal settlement with OSHA on Sept. 10 to reduce a $3,080 fall-protection citation to $1,694, a $2,200 ladders citation to $1,210, a $5,600 scaffolding citation to $3,080 and a $3,080 scaffolding-training citation to $0. The company was issued the citations Aug. 30 during a roofing job at 218 Seventh Ave., New Glarus.

• Martha M. Alvarez, Houston, reached a formal settlement with OSHA on Sept. 11 to pay a $3,300 general-safety-and-health-provisions citation and a $30,800 fall-protection citation. The company was issued the citations Dec. 22 during a roofing job at 200 Spring St., Cambridge. The company also reached a formal settlement Sept. 11 to pay a $3,300 general-safety-and-health-provisions citation and a $30,800 fall-protection citation issued Dec. 22 during a roofing job at 272 Highway 12, Cambridge. The company also reached a formal settlement Sept. 11 to pay a $3,300 general-safety-and-health-provisions citation and a $30,800 fall-protection citation issued Dec. 22 during a roofing job at 609 Milton Ave., Janesville.