APPARENT LOW BIDS
Wisconsin
• Miron Construction Co. Inc., Neenah, submitted the apparent low total bid of $10,089,961 for a terminal building rehabilitation project at the La Crosse Regional Airport.
Sevenson Environmental Services Inc., Niagara Falls, NY, submitted the apparent low bid of $5,242,617 for a harbor improvement project at Menekaunee Harbor in Marinette.
• C3T Inc., Milwaukee, submitted the apparent low bid of $3,105,000 for Phase II work for the Great River Road Interpretive Center project in Genoa.
• Corporate Contractors Inc., Beloit, submitted the apparent low bid of $3,033,390 to construct a new swimming pool and bath house at Sunset Park in Elkhorn.
• SMA Construction Services, Abrams, submitted the apparent low bid of $2,875,843.55 for a terminal build out with site work and apron reconstruction project at the Austin Straubel International Airport in Green Bay.
• Platt Construction Inc., Franklin, submitted the apparent low bid of $2,580,993 for a paint booth HVAC repair and cure booth installation project at Fort McCoy.
• Staab Construction Corp., Marshfield, submitted the only bid of $2,143,000 for a modification project at the Ladysmith Wastewater Treatment Plant.
• Vinton Construction Co., Manitowoc, submitted the apparent low bid of $2,059,647.47 for a bituminous resurfacing project in Sheboygan.
• Zignego Co. Inc., Waukesha, submitted the apparent low bid of $1,856,058 for an airport runway deicing project at the General Mitchell International Airport in Milwaukee.
• M.J. Construction Inc., Milwaukee, submitted the apparent low bid of $1,169,484.50 for a water main relay project in Milwaukee.
• E & N Hughes Co. Inc., Monroe, submitted the apparent low bid of $977,887 for a road reconstruction project in Stoughton and Pleasant Springs.
• Payne & Dolan Inc., Kenosha, submitted the apparent low bid of $675,594.95 for some resurfacing work in Kenosha.
• Elmstar Electric Corp., Kaukauna, submitted the only responsive bid of $659,889 for a security video system improvement project at the Oshkosh Correctional Institution.
• Miron Construction Co. Inc., Neenah, submitted the apparent low bid of $593,769 for an officer station repair project at the Waupun Correctional Institution.
• TL Services Inc., Van Buren, AR, submitted the apparent low bid of $560,270 for a project to integrate and improve utility metering at the Tomah VA Medical Center.
• Granger Builders Inc., Marengo, submitted the apparent low bid of $468,435 to construct a community safe room on the Bayfield County Fairgrounds.
• Peters Concrete Co., Green Bay, submitted the apparent low bid of $296,680 for a dike reconstruction project at the Barkhausen Waterfowl Preserve in Suamico.
• Pride Builders LLC, Marinette, submitted the apparent low bid of $286,893.42 for a heated storage building project in Peshtigo.
• Front Range Environmental, McHenry, Ill., submitted the apparent low bid of $263,038 for a manhole rehabilitation program in Fond du Lac.
• Sonrise Construction Inc., Elkhorn, submitted the apparent low bid of $184,321 for a dam renovation and repair project at the Vern Wolf Lake Dam in Brighton.
• Cardinal Construction Co. Inc., Fond du Lac, submitted the apparent low bid of $182,680 for an addition and remodeling project at the Sheboygan County Rocky Knoll Health Care Center.
• L & T Painting, Clinton Township, Mich., submitted the apparent low bid of $181,000 for a reservoir paint and repair project in Cedarburg.
• New Jobs, Week of July 16 – July 22, 2014: 203
• New Jobs, Week of July 16 – July 22, 2013: 172
• New and Updated Jobs, July 16 – July 22, 2014: 554
• New and Updated Jobs, July 16 – July 22, 2013: 483
• New and Updated Jobs, Jan. 1 – July 22, 2014: 12,684
• New and Updated Jobs, Jan. 1 – July 22, 2013: 10,017
• New Jobs, Week of July 16 – July 22, 2014, by region:
• LaLonde Contractors Inc., Milwaukee, submitted the apparent low bid of $165,226.42 for some paving work in Milwaukee.
• Independence Heating & Cooling LLC, Saginaw, Minn., submitted the apparent low bid of $163,900 for an HVAC replacement project at the Superior WWTP Main Control Building.
• Norcon Corporation, Schofield, submitted the apparent low bid of $163,851 for a parking deck maintenance and waterproofing project in Waukesha.
• Northeast Asphalt Inc., Fond du Lac, submitted the apparent low bid of $101,065.80 for a pavement rehabilitation project in Beaver Dam.
• Mill Coatings Inc., Green Bay, submitted the apparent low bid of $100,775 for an overpass painting project in Kenosha.
• The bid summary for MEP bidders for a 3rd floor renovation project at the Risser Justice Center in Madison can be found HERE.
• The bid summary for MEP bidders for an armory remodeling project in Tomah can be found HERE.
• The MEP bidders bid summary for a pool and splashpad project in Blue Mounds can be found HERE.
Out of State
• Bid-D Construction, Minneapolis, Minn., submitted the apparent low bid of $17,355,000 for the construction of a new National Guard Readiness Center in Stillwater.
• Maertens-Brenny Construction Co., Minneapolis, Minn., submitted the apparent low bid of $1,352,635 for the construction of a bus layover facility in Apple Valley.
• Robert R. Stenstrom Inc., Rockford, Ill., submitted the apparent low bid of $889,647.69 for a citywide street repair project in Rockford.
• Hebert Construction Co., Iron River, Mich., submitted the apparent low bid of $696,600.52 for a sanitary sewer crossings project in Marquette.
AWARDED
• Miron Construction Co. Inc., Neenah, was awarded a $19,758,774 contract to renovate a building on the UW-Stout campus.
• Haas Sons Inc., Thorp, was awarded a $2,690,831.37 contract for a street reconstruction project in Eau Claire.
• J.H. Findorff & Son Inc., Madison, was awarded a $3,227,000 contract for an expansion project at Building D for the Department of Justice in Madison.
• Jossart Bros. Inc., De Pere, was awarded a $2,365,364 contract for a sewer and water improvement project in Oconto Falls.
• Olympic Builders General Contractors Inc., Holmen, was awarded a $2,179,482 contract to construct a police station and civic campus facility in Holmen.
• LaLonde Contractors, Milwaukee, was awarded a $1,813,792.81 contract for some paving work in Milwaukee.
• Radtke Contractors Inc., Winneconne, was awarded a $1,702,403.68 contract for a stormwater improvement project in Calumet and Outagamie counties.
• Haas Sons Inc., Thorp, was awarded a $1,543,474.89 contract for an arterial street construction project in Eau Claire.
• Milwaukee General Construction Co. Inc., Milwaukee, was awarded a $1,199.831.62 contract for some paving work in Milwaukee.
• Albrightson Excavating Inc., Woodville, was awarded a $1,095,393.10 contract for a road extension project in Somerset.
• Ric-Man Construction Inc., Sterling Heights, Mich., was awarded a $1,027,830 contract for an interceptor rehabilitation project in Madison.
• Janke General Contractors Inc., Athens, was awarded a $764,447 contract for a trail construction project at the Upper Yahara River Trail in DeForest.
• ECCO Midwest Inc., Inver Grove Heights, Minn., was awarded a $717,000 contract for asbestos abatement in Harvey Hall at the UW-Stout in Menomonie.
• Miron Construction Co. Inc., Neenah, was awarded a $673,707 contract for a steam/condensate pit project at UW-Oshkosh.
• Maddrell Excavating LLC, Monroe, was awarded a $594,442.50 contract for a street and utility construction project in Sharon.
• Stark Asphalt Service Inc., Milwaukee, was awarded a $559,977.97 contract for some paving work in Milwaukee.
• Angelo Luppino Inc., Iron Belt, was awarded a $472,704 contract for a bike trail construction project on the Northern Highland American Legion State Park in Oneida County.
• Rhom Construction LLC, Eau Claire, was awarded a $456,192 contract for a remodeling project at the Shell Lake campus of the Wisconsin Indianhead Technical College.
• Fischer-Ulman Construction Inc., Appleton, was awarded a $408,700.95 contract for a concrete and street repair project in Appleton.
• Northeast Asphalt Inc., Fond du Lac, was awarded a $291,853.50 contract for a roadway improvement project in Oostburg.
• August Winter & Sons Inc., Schofield, was awarded a $253,920 contract for a pump station replacement project in Lake Mills.
• Dykstra Construction Inc., Ashland, was awarded an $183,578 contract to construct a new office building in the town of Barnes.
• IEI General Contractors Inc., De Pere, was awarded an $180,930 contract for a repair and roof addition project at the Baileys Harbor Marina.
• Scott Construction Inc., Lake Delton, was awarded a $175,432 contract for a seal coating project in Merton.
• Otis Elevator Co., Madison, was awarded a $140,454 contract for an elevator equipment and operations systems upgrade project at the Dodge County Administration Building.
• T & M general Contractors Inc., Reedsburg, was awarded a $58,664 contract for a toilet room renovation project at the Reedsburg City Hall.
• Dave Rybold Excavating & Plumbing, Holmen, was awarded a $55,000 contract to demolish multiple buildings in the village of Holmen.
• Van Offeren Electric LLC, Hilbert, was awarded a $28,989 contract for a power and data project at the Riverside Campus of the Fox Valley Technical College in Oshkosh.
• G & J Concrete Construction Inc., Merrill, was awarded a $26,645 contract for the construction of a concrete apron for the Corning Fire Department.
• Gerber Leisure Products Inc., Mount Horeb, was awarded a $14,300 contract to fabricate a park shelter for the Aldo Leopold Park in Madison.
• Thunder Road Asphalt LLC, Pewaukee, was awarded a $10,883 contract for a crack filling project in Marshall.
• Decker Lumber & Supply General Contractors, Athens, was awarded a contract for roof repairs to the Nokomis Town Hall and Fire Department.
• The award summary for the Ashland County June Timber sale can be found HERE.
• The award summary for the Oconto County Leghorn Timber Sale can be found HERE.
• Springfield Builders Inc., Springfield, MO, was awarded a contract to build an O’Reilly Auto Parts store in Mauston.
Out of State
• Oberstar Inc., Marquette, Mich., was awarded a $5,347,692 contract for a water system improvement project in Newberry.
• DeVere Construction Co. Inc., Alpena, Mich., was awarded a $3,792,000 contract for a WWTP improvement project in Newberry.
• Maneval Construction Co., Grayslake, Ill., was awarded a $671,950.99 contract for a roadway improvement project in Fox Lake.
• Connolly Construction Inc., Peosta, Iowa, was awarded a $419,036.50 contract for a road alignment project in Asbury, Iowa.
• Maintenance Coatings Co., South Elgin, Ill., was awarded a $200,691.85 contract for a city-wide pavement marking project.
• The final award report for the June WisDOT statewide highway letting can be found HERE.
• The final award report for the May WisDOT statewide highway letting can be found HERE.
A/E Services
• Meyer Scherer & Rockcastle Ltd., Minneapolis, Minn., was awarded a contract to provide architect/engineering consulting services for a Madison Municipal Building and City-County Building alterations project.
• HGM Architecture Inc., Oshkosh, was awarded a contract to provide design services for a conversion project at the Outagamie County Law Library.
On the Horizon
• The Rusk County Highway Department is planning a bridge replacement project in the town of Stubbs.
• The Genoa City Village Board has voted to proceed with the construction of a new city hall.
This Week’s Industry Pulse Playlist
Acid Mothers Temple & The Melting Paraiso U.F.O. – Speed Guru
Subtitle – Young Dangerous Heart
Awol One & Factor – Sunset Sandwich
Presage (Outer Perimeter: Presage. Mr Dibbs, Jel, Dose One & Anticon) – The Secret Society
Anticon and Odd Nosdam – Why?
Thavius Beck – Vicious