Catalyst leads collaborative effort on Milwaukee Rehabilitation Hospital

Catalyst leads collaborative effort on Milwaukee Rehabilitation Hospital

By: Jimmy Nesbitt//May 11, 2022//

Listen to this article

The Milwaukee Rehabilitation Hospital at Greenfield opened its doors to the public in late 2021 after a 12-month construction phase led by Catalyst Construction.

Situated on 4 acres on the 3200 block of South 103rd Street in Greenfield, the 15,000-square-foot facility was completed for approximately $17 million and is operated by Nobis Rehabilitation

Partners, an organization that develops inpatient rehab centers throughout the U.S.

The hospital features an outdoor courtyard for walking and therapy, wide lounging corridors for patients and visitors and free on-site parking.

“The actual construction of a rehabilitation hospital is different than most medical buildings,” said Jim Peterson, project manager at Catalyst Construction. “Our team had to account for medical and hospital equipment but also make sure there were plenty open areas for physical therapy and movement.

“Catalyst needed to incorporate all the typical hospital systems but also was required to work with limited space due to large common areas for people, lack of wall space and tall ceilings, which limits ease of mechanical work.”

With 40 private rooms and two therapy gyms, the new three-story inpatient rehabilitation center offers the latest in recovery and rehabilitation technology. The 120-person medical staff provides physical and occupational therapy, rehab nursing and speech-language pathology as well as treatment for patients suffering from debilitating disease, illness, or complex neurological and orthopedic injuries or infirmities.

Construction was completed in December 2021.

“We want to have long lead time items bought out as soon as possible in order to keep the project on schedule,” said Mike Lange, project superintendent for Catalyst Construction. “There was a collaborative effort between Catalyst and all subcontractors; work never not stopped on the job site. It took some creative effort to complete some tasks out of sequence in order to hand over the building on time.”

Milwaukee Rehabilitation Hospital at Greenfield

Location: Greenfield

Cost: $16,040,000

Start: November 2020

Completion: December 2021

Owner/Developer: WB Development Partners

Architect: Perkins & Will

Other Associates: NEC Milwaukee LP (manager), Excel (commissioning agent for owner), Nobis Rehabilitation Partners (operator representative), McCrackin Project Management (project manager representative), WE Energies – Relocate, Office of Plan Review and Inspection

Construction Manager: Catalyst Construction

Submitting Company: Catalyst Construction

Subcontractors: Alpha Insulation & Waterproofing, AMCS, Applewood Drywall Services, Applewood Plastering Service, AVAdek, Best Specialties, Blair Fire Protection, Bliffert Lumber & Fuel, Block Iron & Supply, BMCI Construction/T.P. Concrete Services, Boelter Food Service Design, Equip & Supply, Cardinal Fabricating, Construction Specialties, Craftmaster Painting, D & L Grading, DF Tomasini Contractors, Earth Care Window Treatment, Flag Center (MMK Enterprises), Floor 360, Geis Building Products, JM Brennan, JWC Building Specialties, K.G. Stevens, Klein Dickert, Muza Sheet Metal, Neumann, Pinnacle Engineering Group, Preferred Electrical Contractors, Quality Ceilings, Regency Janitorial Service, Schindler Elevator, Schranz Roofing, Sid’s Sealants, Storage Concepts, Superior Masonry, Trees on the Move, Trim Specialists, Wolf Paving

Photo Credit: Logan Zweifel

No tags for this post.

Polls

Do you expect your business to grow revenue in 2026 vs. 2025?

View Results

Loading ... Loading ...

Today’s News

See All Today's News

Project Profiles

See All Project Profiles