Top Projects of 2025: Alto-Shaam Building Expansion

Top Projects Voting 2026

Top Projects of 2025: Alto-Shaam Building Expansion

By: Daily Reporter Staff//May 8, 2026//

Listen to this article

Alto Shaam’s 128,000-square-foot building expansion at its Menomonee Falls, Wisconsin, global headquarters represents a landmark achievement in private construction, completed June 1, 2025, at a cost of $21 million. The project delivered a state-of-the-art Innovation Center, fully equipped research and development laboratories, expanded warehousing and shipping facilities, and new office and collaboration spaces designed to support long-term operational and manufacturing growth.

The expansion presented significant challenges, including supply chain pressures, schedule constraints and structural complexities. COVID-19 had delayed the project’s initial plans, but Alto Shaam revived and expanded the initiative, ultimately delivering a modern, future-focused facility. Phased construction planning, full-time onsite safety supervision and bi-weekly third-party SiteGuard Safety inspections kept operations running safely throughout all phases.

The project incorporated superflat floor tolerances for high-precision pallet storage, advanced material handling systems, cutting-edge test bays and digital manufacturing enhancements — elements rarely combined in manufacturing expansions of this scale.

The outcome strengthens Alto Shaam’s position as a major employer in Menomonee Falls and supports the company’s reach into more than 100 countries worldwide. Energy-efficient lighting, mechanical systems and improved workplace ergonomics further enhance the facility’s long-term value. Moore Construction Services, MC Group, Excel Engineering and the City of Menomonee Falls were critical partners in delivering the project.

Project Essentials

Location: Menomonee Falls

Cost: $21,000,000

Complete: June 2025

Owner/Developer: Alto-Shaam

Architect: Excel Engineering

Engineers: Excel Engineering, CJ Engineering

Interior Designer: Kahler Slater

General Contractor: Moore Construction Services

Submitting Company: Moore Construction Services

Subcontractors: Advantage Acoustical, Arbon Equipment, Cardinal Fabricating Corp., Carlson Racine Roofing & Sheet Metal, Chris Greene, Craftmaster Painting, D&L Grading, H.J. Martin and Son, Hamilton Industries, JC Building Systems, Kevco, Inc., Klein-Dickert, LaForce, Maly Ceramic Tile Co., Marriott Construction, Midwest Drilled Foundations & Engineering, Mukwonago Garage Door, Northway Fence, Payne & Dolan, Rock Solid, Sciachitano Caulking, Soper Companies, SRS Roofing, Stonecast Products, Total Mechanical, Villani Landshapers, Wandel Contractors, Wisconsin Window Concepts, Workspace Studio

Click here to see all the Top Projects of 2025

Polls

Do you expect your business to grow revenue in 2026 vs. 2025?

View Results

Loading ... Loading ...

Today’s News

See All Today's News

Project Profiles

See All Project Profiles