Froedtert Advanced Care Center overcomes plan changes, weather

Froedtert Advanced Care Center overcomes plan changes, weather

Listen to this article

 

Change might be a good thing.

But that doesn’t mean it’s not difficult.

Just ask the team behind the new Advanced Care Center at Froedtert Hospital and the Medical College of Wisconsin.

When the 608,000-square-foot center’s plans were approved, it was to have four levels above grade and three levels of underground parking.

“That’s where it started,” said Jeff Gruhn, general manager of health care at Mortenson Construction, which oversaw the construction of the $142 million project.

The very next day, Gruhn’s team was asked to add a fifth floor to the building — with no additional money or leeway in the construction schedule.

“So right away on Day 1 we were over-budget,” Gruhn said. “That was our very first challenge.”

As the construction of footings and foundations began, the project owners asked to explore the possibility of building another four floors — still with no change to the scheduled completion date.

“They built this building to move programs out of the way so we could start on a major surgery platform renovation, so the timing of that was absolutely critical for them from a revenue standpoint,” Gruhn said.

To make it work, Gruhn and his colleagues put in a temporary roof layer inside the building, allowing crews to continue working on the floors below at the same time that the shell and core were put in for the four additional floors.

And, Gruhn said, “We started this project during one of the most challenging winters on record. That’s when we were bringing this building out of a hole in the ground.”

They lost time on the front end. But the center, which houses the Heart and Vascular Center and Transplant Center and gives surgery patients a new entrance, opened on time in October 2015.

“We had our challenges but we met our original schedule,” Gruhn said.

In fact, he added, “We actually were able to get that additional floor incorporated with no budget or schedule relief.”

[youtube http://www.youtube.com/watch?v=EPt49byZuno]

essentials

Froedtert & the Medical College of Wisconsin Center for Advanced Care

Location: Milwaukee, Wisconsin

Project size: 608,000 square feet

Project cost: $142 million

Start date: June 2013

Completion date: December 2015

Submitting company: Mortenson Construction

General contractor: Mortenson Construction

Architect: CannonDesign

Architect: Zimmerman Archtectural Studios

Engineer: CannonDesign

Owner: Froedtert & the Medical College of Wisconsin

No tags for this post.

Polls

Do you expect your business to grow revenue in 2026 vs. 2025?

View Results

Loading ... Loading ...

Today’s News

See All Today's News

Project Profiles

See All Project Profiles