Neenah High School

Neenah High School

By: Daily Reporter Staff//May 16, 2024//

Listen to this article

Building the new Neenah High School — the second largest in Wisconsin — required effective coordination and communication to finish on time so students could begin the 2023-24 school year.

“This sheer size of this project was a challenge and unique compared to others,” said Tyler Crisp, project manager for Miron Construction, the project’s general contractor. “We did not start building vertical until February of 2022, so really we built a 460,000-square-foot school in roughly 18 months. That is pretty special in my mind.”

Coordination was a must with more than 1,875 workers on-site, 94 primary contractors and suppliers, 11 bid packages, 59 construction bulletins and more than 700 requests for information on the project.

The school complements the entire student experience — academics, activities, arts and athletics — and facilitates student and educator collaboration. The school includes flexible, hands-on learning environments, state-of-the-art tech ed shops for welding, autos, robots and engineering, an auditorium and black box theater, a large gym, a wrestling gym, a fitness center, large parking areas and outdoor sports fields.

Crisp said the project posed a challenge due to its sheer size and the amount of design team members, contractors and district stakeholders involved. A significant amount of communication was necessary to keep the project on track and ensure everyone was informed as the project progressed, he added.

Miron utilized the masonry MULE (Material Unit Lift Enhancer) on the project to improve project safety and efficiency. MULE serves as an extension of workers’ hands, doing the heavy lifting while the masons place the block.

Neenah High School

Location: Neenah

Cost: $158M

Start: Summer 2021

Complete: July 2023

Owner/Developer: Neenah Joint School District

Architect: Bray Architects

Engineers: Point of Beginning, MSA Professional Services, Fredericksen Engineering

General Contractor: Miron Construction

Submitting Company: Miron Construction

Other Significant Project Participants: Ambrose Engineering, Huffman Keel Partners

Subcontractors: Altmeyer Electric, Appleton Lathing Corp., Arrow AV Group, Baseman Floors, Blair Fire Protection, Bradford Systems, CM Morris Group, Corcoran Glass & Paint, Crafts, Daktronics, Discher Arch Millwork, Endres Manufacturing Co., Energy Control & Design, Fisher Tracks, GO Loop, Gopher Stage Lighting, H2I Group, HJ Martin & Son, Hurckman Mechanical Industries, JW Industries, JWC Building Specialties, Keeper Goals, LaForce, Macco’s Commercial Interiors, Martell Construction, Masse’s Floor Coatings, MCC, Midwest Sport and Turf Systems, Muza Sheet Metal Co., Northway Fence, Otis Elevator Co., Overhead Door Company of Appleton, Performance Firestop, Peterson Companies, Point of Beginning, ProStar Surfaces, Pukall Co., Reliable Door and Dock, Reschs Tile, Schmalz Custom Landscaping & Garden Center, Specialty Closures & Equipment Co., Spectrum Maintenance Services, Spirit Fabs, Standard Wire & Steel Works, Stratford Sign Sales, The Boelter Companies, The Sprinkler Company, TLC Sign, Tweet Garot Mechanical, Valley Sealcoat, Van Ert Electric Co., Veit & Co., Wausau Tile, Wells Concrete, Wm A Hein Construction Co., Wynn O Jones & Associates, Zander Solutions.