BMO Tower to embark on 25-hour concrete pour this weekend

(Staff photo by Kevin Harnack)

(Staff photo by Kevin Harnack)

(Staff photo by Kevin Harnack)

Crews work around the clock to pour the foundation of the new Irgens’ BMO Tower Saturday, June 2 in Milwaukee. J.H. Findorff and Son is overseeing construction of the project which includes the pour which began and midnight Saturday and is expected to run for 25 hours. The pour marks the start of start of vertical construction on the site and 6,700-cubic-yards of concrete are expected to be used during the pour. Wells Street along the project the project is closed for the duration of the pour. The tower is expected to be complete in 2019. (Staff photo by Kevin Harnack)

(Staff photo by Kevin Harnack)

Crews work around the clock to pour the foundation of the new Irgens’ BMO Tower Saturday, June 2 in Milwaukee. J.H. Findorff and Son is overseeing construction of the project which includes the pour which began and midnight Saturday and is expected to run for 25 hours. The pour marks the start of start of vertical construction on the site and 6,700-cubic-yards of concrete are expected to be used during the pour. Wells Street along the project the project is closed for the duration of the pour. The tower is expected to be complete in 2019. (Staff photo by Kevin Harnack)

(Staff photo by Kevin Harnack)

(Staff photo by Kevin Harnack)
Crews work around the clock to pour the foundation of the new Irgens’ BMO Tower Saturday, June 2 in Milwaukee. J.H. Findorff and Son is overseeing construction of the project which includes the pour which began and midnight Saturday and is expected to run for 25 hours. The pour marks the start of start of vertical construction on the site and 6,700-cubic-yards of concrete are expected to be used during the pour. Wells Street along the project the project is closed for the duration of the pour. The tower is expected to be complete in 2019. (Staff photo by Kevin Harnack)

Think you’ve got a busy weekend ahead? It could be worse.

On Saturday, crews will embark on a 25-hour concrete pour to lay the foundation of the proposed BMO Harris Tower in downtown Milwaukee. When finished, the work will constitute one of the largest concrete pours in state history.

Mokena, Illinois-based Ozinga Bros. will supply concrete for the massive pour, which is scheduled to start at midnight on Friday and run into the wee hours of Sunday morning. The tower’s foundation will require some 6,000 cubic yards of concrete, weighing 24 million pounds, delivered in more than 600 truck loads.

Crews broke ground on the BMO Tower in November, replacing a parking garage across from city hall. In early April, crews erected a 280-foot-tall crane to assist with vertical construction as work wrapped up on the building’s foundation.

BMO Harris Bank and the law firm Michael Best & Friedrich have signed on to be the building’s biggest tenants. The law firm itself has already committed to occupying about 50 percent of the tower’s office space, Rob Oldenburg, vice president of development at Irgens Partners, the tower developer, said in April. The commercial real estate firm Colliers International is marketing the remaining space.

Kahler Slater, an architecture firm out of Milwaukee, designed the glass tower and Madison-based J.H. Findorff & Son is the general contractor working on the project. Crews expect to complete about 10 stories of the project— dedicated for a parking garage — by the end of the year. The remaining 14 stories will be used for office space.

Correction: A previous version of this story incorrectly identified how much concrete will be used in the foundation of the BMO Tower. We regret the error.

About Nate Beck, nbeck@dailyreporter.com

Nate Beck is The Daily Reporter's construction staff writer. He can be reached at (414) 225-1814 (office) or 414-388-5635 (mobile).

Leave a Reply

Your email address will not be published. Required fields are marked *

*