1. AMOUNT: $4,100,000
AWARDED TO: Terra Engineering & Construction Corp., Madison
PROJECT: Steam system work at Winnebago Mental Health Institute in Oshkosh
2. AMOUNT: $1,727,000
AWARDED TO: Joe Daniels Construction Co. Inc., Madison
PROJECT: Utility improvements at the University of Wisconsin-Madison
3. AMOUNT: $1,390,000
AWARDED TO: Terra Engineering & Construction Corp., Madison
PROJECT: Utility connections at the University of Wisconsin-Madison
4. AMOUNT: $1,269,833
AWARDED TO: Rule Construction Ltd., Dodgevill
PROJECT: Street reconstruction in Platteville
5. AMOUNT: $999,159
AWARDED TO: Lee Recreation, Cambridge
PROJECT: Playground equipment in Platteville
6. AMOUNT: $895,000
AWARDED TO: Hooper Corp., Madison
PROJECT: Utility connections at the University of Wisconsin-Madison
7. AMOUNT: $724,900
AWARDED TO: Sure-Fire Inc., Horicon
PROJECT: HVAC work at the Army National Guard Headquarters in Madison
8. AMOUNT: $389,000
AWARDED TO: Universal Power & Systems Inc., Madison
PROJECT: Electrical work at the Army National Guard Headquarters in Madison
9. AMOUNT: $348,900
AWARDED TO: Riley Construction Co., Kenosha
PROJECT: Renovation at dust collection system at UW-Parkside, Kenosha
10. AMOUNT: $302,854
AWARDED TO: Ritola Inc., Mason
PROJECT: Sewer relocation in Washburn