• Overhead Solutions Inc., Green Bay, reached an informal settlement with OSHA on April 2 to reduce two scaffolding citations, totaling $8,400, to $2,000. The company was issued the citations March 5 during a roofing job at 215 S. Main St., Brillion.

• Spray-O-Bond Co., Milwaukee, reached an informal settlement with OSHA on April 3 to reduce a $1,836 stairways-and-ladders citation to $0. The company was issued the citation March 13 during a masonry job at 509 W. Wisconsin Ave., Milwaukee.

• Willkomm Excavating & Grading Inc., Union Grove, reached an informal settlement with OSHA on April 3 to reduce a $30,250 specific-excavation-requirements citation to $22,000 and a $30,250 requirements-for-excavation-protective-systems citation to $5,000. The company was issued the citations March 12 during a site preparation job at 10600 W. Layton Ave., Greenfield.

• Cost of Wisconsin Inc., Jackson, reached an informal settlement with OSHA on April 4 to reduce a $2,524.50 welding-cutting-and-brazing citation to $1,270. The company was issued the citation March 13 during a specialty trade job at 4201 County Road P, Jackson.

• Helmer Construction, Oregon, reached a formal settlement with OSHA on April 11 to reduce a $4,200 eye-and-face-protection citation to $1,200, a $4,200 fall-protection citation to $1,200 and a $3,000 ladders citation to $1,000. The company was issued the citations Nov. 21 during a roofing job at 7324 Summit Ridge, Middleton.

• Mid-American Fiber Construction Inc., Franksville, reached an informal settlement with OSHA on April 11 to reduce a $4,200 vehicle-mounted-elevating-and-rotating-work-platform citation to $1,500. The company was issued the citation Feb. 27 during a power- and communication-line job in Kenosha.

• STS Roofing Inc., Muskego, reached an informal settlement with OSHA on April 11 to reduce a $2,040 ladders citation to $0, increase a fall-protection citation from $0 to $700 and dismiss a $2,040 scaffolding citation. The company was issued the citations March 23 during a roofing job at 1360 S. 57th St., West Allis.

• James W. Quigley Construction, Osceola, reached an informal settlement with OSHA on April 11 to reduce a $3,000 specific-excavation-requirements citation to $1,500 and a $4,200 requirements-for-excavation-protective-systems citation to $2,100. The company was issued the citations March 23 during a site preparation job at 175 Depot Road, Osceola.

• Madison Remodeling Roofing & Siding, Madison, reached an informal settlement with OSHA on April 13 to reduce a $4,200 fall-protection to $1,500 and a $4,200 fall-protection-training citation to $0. The company was issued the citations Jan. 18 during a roofing job at 4526 Ellington Way, Middleton.

• Kadlec Electric Inc., Rhinelander, reached an informal settlement with OSHA on April 13 to reduce a $1,430.55 electrical-installation-safety-requirements citation to $0. The company was issued the citation March 21 during an electrical job in Appleton.

• Osceola Plumbing & Heating Inc., Osceola, reached an informal settlement with OSHA on April 16 to reduce a $4,200 requirements-for-excavation-protective-systems citation to $2,100 and a $1,800 ladders citation to $900. The company was issued the citations March 23 during a plumbing, heating and air conditioning job at 175 Depot Road, Osceola.

• Javier Arciniega Drywall, Sheboygan, reached an informal settlement with OSHA on April 18 to reduce a $2,400 eye-and-face-protection citation to $1,500. The company was issued the citation March 26 during a drywall and insulation job in Fond du Lac.

• Esquire Construction Ltd., Kenosha, reached an informal settlement with OSHA on April 19 to pay a $4,620 fall-protection citation and to reduce a $3,300 material-handling-equipment citation to $1,750 and a $4,620 fall-protection-training citation to $0. The company was issued the citations April 3 during a framing job at 12400 N. Ville du Parc Drive, Mequon.

• Advanced Electric LLC, Fond du Lac, reached an informal settlement with OSHA on April 19 to reduce a $2,040 electrical-wiring-methods citation to $1,000. The company was issued the citation March 27 during an electrical job in Fond du Lac.

• Integrity Environmental Services Inc., Waukesha, reached a formal settlement with OSHA on April 23 to pay a $1,517 safety-training-and-education citation. The company was issued the citation Oct. 20 during a remediation job at 3205 W. Wisconsin Ave., Milwaukee.

• Jim’s Plumbing & Heating Inc., Greenville, reached an informal settlement with OSHA on April 23 to reduce a $3,000 head-protection citation to $1,600 and a $3,000 requirements-for-excavation-protective-systems citation to $2,100. The company was issued the citations April 9 during a plumbing, heating and air conditioning job at 4500 W. College Ave., Appleton.